Oman
Co-generation Power Plant
|
|
| |
Client: |
|
Oman Refinery Company |
|
|
| |
Project type:
|
|
Lump Sum Turn Key (LSTK) |
|
|
|
|
Scope of
Work: |
|
|
PBasic
Design |
|
PDetail
Engineering |
|
PLocal
and Foreign Procurement |
|
PConstruction |
|
PCommissioning |
|
|
|
| |
Brief
description: |
|
|
P2x25 MW Gas
Turbine |
|
P2x100 TPH,
HRSG |
|
Px30 TPH,
Supplementary FiringAux. Boiler |
|
PDesalination
Plant |
|
PPolishing
Plant |
|
PFuel Gas
Conditioning |
|
PWarehouse
Re-location |
|
|
| |
Location: |
|
Oman Refinery Co.
Muscat. Sultanate of Oman |
|
|
| |
Project Period:
|
|
28 Months |
|
|
|